European Parliament negotiators and the Council of the European Union have reached a provisional agreement to accelerate permits for renewable energy projects, electricity grids, energy storage facilities and electric vehicle charging stations. The deal aims to reduce delays in expanding Europe’s clean-energy infrastructure and help lower energy costs.

The agreement would establish shorter approval deadlines and a single national digital portal for permitting procedures. Deadlines would range from three months for solar equipment and co-located storage to two years for pumped hydropower storage. Grid connection decisions would generally be required within three months, with extensions allowed in justified cases.

Negotiators also agreed to raise the threshold requiring permits for small-scale solar installations, energy storage and charging stations from 100 to 200 kilowatts. Charging stations with a total capacity of up to 1 megawatt would not require administrative permits when installed on artificial structures.

Projects exceeding 7 megawatts would be required to share economic benefits with local communities, down from the previously proposed 10-megawatt threshold. The agreement still requires approval by Parliament’s Industry, Research and Energy Committee, the full Parliament and the Council before it can be published in the EU’s Official Journal.